Before you sign
the lease
Most secure facility problems are decided long before anyone draws the space. They are decided on the day a lease is signed. This page is a site selection checklist for secure facilities, and a second module that compares leasing, building and the flexible options against your own constraints. Both run entirely in your browser. Neither one gives you an answer about the building; both give you the questions to take to it.
The problem: real estate decides the project
A bad real estate decision creates security, construction, accreditation and schedule problems later, and it creates them in that order. The building sets what can be built in it. What can be built sets what can be accredited. What can be accredited sets when the work can start. By the time any of that surfaces, the lease has been signed and the cheapest fixes are gone.
None of this is exotic. The facts that matter are ordinary building facts: what the lease permits, what the structure carries, where the services run, who else is in the building, what the local jurisdiction requires, and who is available to do the work. They are all knowable before signature, and most of them are cheap to check. They are simply not on the list a broker hands you, because the requirement they serve is not a requirement most tenants have.
This page is that list. It is deliberately generic. It is about what to verify, not about how any particular building is protected.
What usually goes wrong
The most expensive mistake available on this page. A lease is signed on the strength of rent, location and square footage, and the secure requirement is handed to a designer afterwards. Everything that follows is then constrained by a document nobody read for this purpose.
Alteration rights, roof and riser access, who pulls the permits, what happens to the build at the end of the term: all of it is contractual. A building that physically suits the requirement can still be the wrong building because of what the lease will not let you do to it.
Floor loading is a fact about the building. When it turns up during design rather than during selection, the options left are to reduce what goes in the space, reinforce the structure at cost, or move. All three are worse than looking earlier.
Cable routes, mechanical access and a path to the roof decide how much of the design is possible. Space that is beautiful on a floor plan can be unworkable once you trace where the services actually have to run.
Shared walls, shared risers, shared entrances and the tenants on either side are part of your project whether or not you want them to be. Tenant turnover across a ten year term is part of it too.
Real estate, construction and accreditation each run on their own calendar. A schedule built backwards from the award date, rather than forwards from those three, produces a facility that is late in a way nobody can recover.
What you need to know
How do you evaluate a facility before signing a lease?
How do you decide between permanent and modular secure space?
Why do facility and contract schedules diverge?
Check your site
Two modules. The first walks the fifteen things worth verifying before a lease is signed, and tells you which of them still need answers and roughly in what order. The second sets the ways of getting secure space against your own constraints, so the trade-offs are visible before you commit to one. Nothing is transmitted unless you ask for it.
The site selection checklist
Fifteen items, in six groups, each with the reason it matters. Mark each one as checked, not yet, or not applicable to this site. Anything you mark not applicable leaves the picture rather than counting against you, and anything you leave alone stays on the list of things to verify before signing.
Before you sign the lease
Secure facility site selection checklist · saliandefense.com/site-selection.html
Do not enter classified facility details or the address of a facility that will hold classified information. Planning-level answers only.
Rights and neighbors
- Landlord restrictions and construction rightsThe lease decides what you are allowed to build. Alteration rights, approval timelines, who holds the permits and what you must restore at the end are all settled in the document, and they are far harder to change after signature.
- Roof and riser accessMechanical equipment, antennas and cable routes need a path to the roof and through the building risers. Those paths are granted in the lease, or they are not available to you at all, and shared risers come with shared conditions.
- Penetrations and shared wallsEvery wall you share with another tenant, and every existing penetration through the envelope, becomes a design question later. Finding them before signature costs a walkthrough; finding them during construction costs a change order.
- Adjacent tenantsWho occupies the floors above, below and beside you affects noise, vibration, shared access and the questions your security officer will ask first. Tenant turnover during your term matters as much as who is there on the day you look.
Structure and building systems
- Floor loading and slabSecure construction, storage containers, equipment and mechanical plant are heavy. The live load capacity of the floor is a structural fact about the building, and it is one of the few facts a landlord cannot concede to you.
- Mechanical access and HVAC independenceWhether you can run heating, cooling and ventilation independently of the base building, and reach that plant for maintenance without leaving your own space, shapes the design, the operating cost and how much you depend on the landlord.
- Secure pathways and cabling routesCable has to travel from where it enters the building to where it is used, along routes you control. A building that makes that route awkward makes everything downstream of it slower and more expensive.
The site and its approaches
- Parking and controlled accessWhere people park, how they enter, and where deliveries arrive are facts about the site rather than choices you make later. A building with a single shared entrance constrains what you are able to arrange inside it.
- Setbacks and external exposureThe distance between your space and ground that other people control is set by the site. It is worth measuring before you sign, because it is the one dimension you cannot add to the building afterwards.
Connectivity and utilities
- Network availability and carrier diversityWhich carriers already serve the building, and by how many separate physical paths they enter it, decides both what you can order and how long it takes. A new entrance facility is measured in months, not weeks.
- Generator and utility redundancyWhether the building has standby generation, whether any of it is available to you, and where a generator of your own could stand are questions with a physical answer on every site. Ask them before the lease, not during design.
Growth and approvals
- Expansion capacityContiguous space you could take later, and the contractual right to take it, are worth more at signature than they cost. Growing into a second building in another part of town is the expensive alternative.
- Zoning and permittingLocal zoning, permitting timelines and any historic or overlay designation on the building sit outside your control and inside your schedule. They are public records, and they are cheap to check before the lease.
Delivery and schedule
- Local labor and cleared tradesSecure construction needs trades that can work under the conditions the project requires, and there are markets where those trades are scarce or booked a year out. Availability is a local question with a local answer.
- Schedule fit against the contract dateReal estate, construction and accreditation each run on their own clock, and none of the three runs on the contract award date. Add them up honestly and compare the total against the date you have already committed to.
This checklist is planning guidance only. It is not engineering, legal, real estate or accreditation advice, and it is not a determination by any government authority. Site conditions, lease terms and local requirements vary, and every item here is a question for a qualified professional about the specific building in front of you. Accreditation rests with the applicable Accrediting Official or Cognizant Security Authority. Do not enter classified facility details.
The download opens your browser's print view, which prints or saves the checklist as a file. The email button opens your own mail client with the checklist already in the body. Neither one sends anything to Salian, and neither one asks you to give up an address to read the result.
Should we lease, build, or use a flexible solution?
Six ways of getting secure space, set against nine things about your situation. The module returns a table, not an answer. Where an option is a poor fit for one of your constraints, the table says so and says why, and you decide what you are willing to trade.
- Company-owned facilityYou buy or already own the building. The most control and the most capital, and the option that takes longest to stand up.
- Long-term leaseOrdinary commercial space taken for a long term and fitted out for the requirement. The most common answer, and the one where the lease language does the most work.
- Short-term leaseThe same arrangement on a term short enough that the fit-out may outlive it. Low commitment, and the commitment is the point.
- Secure coworking or shared accredited environmentsSpace someone else holds and operates, taken by the seat or by the room, where such an arrangement is available and acceptable to the customer.
- Modular or mobile facilitiesPurpose-built units delivered to a site rather than constructed in place. Faster to stand up, and reversible, at the cost of the site work around them.
- Customer-site executionYour cleared people work inside a facility the customer already holds. Nothing to build, and no facility of your own to carry.
Methodology
Nothing here is judged and nothing is weighted. Each item is either verified, still to verify, or retired as not applicable, and the picture is your own answers restated in the order this work is usually done. Items you mark not applicable leave the picture rather than counting against you. Nothing you enter leaves your browser unless you ask for it.
This comparison does not pick an option for you. It sets out the trade-offs so that the choice you make is the choice you meant to make.
This checklist is planning guidance only. It is not engineering, legal, real estate or accreditation advice, and it is not a determination by any government authority. Site conditions, lease terms and local requirements vary, and every item here is a question for a qualified professional about the specific building in front of you. Accreditation rests with the applicable Accrediting Official or Cognizant Security Authority. Do not enter classified facility details.
What Salian does
Walking a shortlisted site with the security requirement in hand, and saying plainly which of the items on this page it satisfies, which it complicates, and which of them would need a specialist before you commit. Done before the lease, this is the cheapest work on the whole project.
Reading the contract, the DD-254 or the program requirement for what it actually obliges you to build, so that a site can be judged against something specific rather than against a general wish for secure space.
Design coordination, construction management, and accreditation package preparation with coordination through the applicable Accrediting Official or Cognizant Security Authority, then sustainment after occupancy. One schedule and one accountable contract rather than five vendors and the seams between them.
Modular and mobile units are delivered through cleared partners under Salian's schedule. Where the honest answer is an interim arrangement while something permanent is built, we will say so, and we will help you sequence the two.
What Salian does not control
Nothing on this page is a determination, and nothing on it is a promise about a building. The applicable Accrediting Official or Cognizant Security Authority accredits the facility. Salian prepares the package and coordinates the process, and cannot commit the outcome on the authority's behalf.
The rest of the list belongs to other people too. The landlord decides what the lease permits. The local jurisdiction decides zoning and permits. A structural engineer, not a checklist, establishes what a floor will carry. Counsel, not a website, reads your lease. This page is written so you know which question belongs to whom before you are committed to a building.
What happens next
- Walk the checklist above for each candidate building, and take the printable version with you when you visit. A site you cannot answer for is a site you do not yet know.
- Run the comparison if the shape of the answer is still open. If it points somewhere other than a lease, that is a real result and it is cheaper than the lease.
- Scope the requirement properly in the project readiness tool before design money is committed.
- Take a planning range from the secure facility cost estimator, and compare it against what the building will let you do.
- If a facility clearance is also in front of you, work the gates in the FCL readiness self-check, because that clock runs alongside this one.
- Send us the picture if you would like a second opinion on a shortlist. We reply within one business day, and we will tell you when the honest answer is that you do not need a facility at all.
Sources
The public authorities behind the items on this page, all retrieved 2026-09-02. They are a starting point for your own reading and for professional review, not a substitute for either. Local building and fire codes, and any program-specific requirement, sit on top of them.
- ICD-705 Intelligence Community Directive 705 and the related IC standards, which set the construction and management requirements for SCI facilities. Office of the Director of National Intelligence. dni.gov, Intelligence Community Directives
- ICS 705-1 and the IC technical specifications The physical and technical construction specifications that sit under ICD-705, including the construction and TEMPEST-related considerations that make some buildings harder to work with than others. ODNI and the National Counterintelligence and Security Center. dni.gov, IC technical specifications for SCIF construction and management
- GSA leasing guidance The General Services Administration's public leasing policy and desk guide material, useful as a reference for how lease terms, tenant improvements and expansion rights are ordinarily structured. General Services Administration. gsa.gov, leasing guidance
- International Building Code, live loads Chapter 16 of the International Building Code, section 1607, for how floor live loads are established and documented. International Code Council. codes.iccsafe.org, IBC chapter 16, section 1607